Project start date: 2nd MAY 2025
Our building project in Welwyn Garden City consists of demolition to remove an existing single garage and rebuilding a single extension.
We have so far completed works;
Removing the existing garage & waste removal from site
Due diligence works for the S.E design;
Expose existing garage foundation @ 1.5m
Expose existing concrete slab
Expose existing house foundation for adequate steelwork foundation
(All confirmed with S.E for re-use where possible)
Excavate & C25 concrete foundation to 1.4m
Excavate & install new 1m3 soak-away and underground rain water pipework
New 1.2m x 1.2m window opening with cavity wall lintel installation
3m Steelwork installation & pier rebuilds
Light has been well considered for this project, with multiple new windows adding duel aspect, a large 2m x 1m flat roof window & patio doors.
The build will open up the downstairs floor plan with doors leading to the patio - as well as adding an additional room & practical space.
Our project hopes to enhance our clients way of life and their way to enjoy the view of their much loved garden…